Request Consultation

Data Centre Commissioning
Authority (CxA)

Specialized, Independent Commissioning:
Greenfield Builds and Existing Facilities
Illustrative commissioning environment in a liquid-cooled AI data hall, identifying details intentionally obscured

Integrated systems testing in a liquid-cooled AI data hall. Illustrative; identifying details intentionally obscured.

Gated L0–L5 verification, from design review through integrated systems testing, that finds risk early and proves performance before handover.

MCE is a Canadian-owned Commissioning Authority, independent of design and construction, supporting owners as Canada builds its sovereign AI and data centre capacity.

Senior engineering leadership brings more than twenty years of mission-critical engineering experience. Purpose-built for gigawatt-scale data centre campuses. Reviewed data centre designs across the globe. Led by P.Eng.-licensed engineers, MCE acts solely as the owner's representative.

What Does a Data Centre Commissioning Authority Do?

Commissioning is the systematic verification that a facility performs as an integrated whole, in accordance with the Owner's Project Requirements and the Basis of Design. Installation confirms that equipment is in place. Commissioning confirms that it performs — individually, together, and under the conditions the facility was designed to meet.

MCE acts as Commissioning Authority on behalf of the owner. We hold no design interest and no construction interest in any project we commission, and our findings are reported to the owner against the specification, without obligation to any other party on the project.

The value to the owner is direct. Deficiencies are identified and resolved within the construction contract, while responsibility still rests with those who built the facility. Integration issues that cross vendor boundaries are found during testing rather than in service. Systems are placed into operation with their performance demonstrated, witnessed and documented rather than assumed.

Greenfield and Existing Facility Commissioning

Greenfield Data Centre Commissioning

New builds commissioned from design review through integrated systems testing and turnover, under the full L0–L5 framework.

Existing Facility Commissioning

For the built environment: expansions, retrofits and equipment replacements in operating facilities, and recommissioning of existing systems against current load and the owner’s requirements.

Hyperscale Data Centre Commissioning

Hyperscale and Gigascale Campuses

MCE brings a purpose-built approach to commissioning hyperscale and gigascale data centre campuses, run on the MCX™ platform.

MCX™ Data Centre Commissioning Platform

Commissioning runs on the Mission Critical Commissioning Platform (MCX™), engineered for consistency: checklists and test scripts with the parameters and acceptance criteria built in. Progress is gated by witnessed, signed results, so the integrity of the commissioning process is enforced by the platform itself.

This makes commissioning rigorous and repeatable across complex projects, with every result traceable to its signed record. Every party works in a browser, in the office or in the field, with or without a connection. Project data is stored and processed in Canada.

See how we deliver on MCX™ →

Read: What does a commissioning project need? →

Every test is engineered before the equipment arrives.

Procedures, parameters and acceptance criteria, engineered to MCE’s commissioning standard.

Commissioning Levels L0–L5

Test run.
You are the scroll wheel.

TEST RUN Illustrative
UNIT-001Equipment unit · L1 — Factory test
Illustrative record
No.Check item · procedureAcceptanceResult
1Check itemSpecified test procedureSpecified acceptance limitRecorded result✓
2Check itemSpecified test procedureSpecified acceptance limitRecorded result✓
3Check itemSpecified test procedureSpecified acceptance limitRecorded result✓
4Check itemSpecified test procedureSpecified acceptance limitRecorded result✓
5Check itemSpecified test procedureSpecified acceptance limit____Recorded result✓
Tested byManufacturer's representative✓ signed
Reviewed byCxA✓ signed
Witnessed byOwnerawaiting✓ signed
Commissioning progress · illustrativeRead from the signed records · each level advances on witnessed, signed results
L0 Design Review 0% Queued OPR · BOD · drawings · submittals · design issues
L1 Factory Testing 0% Queued Type Test per Model · FAT per unit, witnessed
L2 Delivery & Installation 0% Queued Delivery · Installation Quality
L3 Pre-Functional & Startup 0% Queued PFT · Startup · TAB
L4 Functional Performance Testing 0% Queued FPT per unit · sub-system FPT scripts
L5 Integrated Systems Test 0% Queued Integrated systems test scripts for the structure
✓ COMMISSIONED
All six levels complete, witnessed, and recorded.
Six levels, from design review through factory testing, delivery and installation, pre-functional testing and startup, and functional testing to the integrated systems test, in one record.

Commissioning Scope: Power, Cooling and Controls Systems Verified

Commissioning scope is defined in the Commissioning Plan and agreed with the owner at the outset. On data centre projects, MCE's scope typically covers:

Electrical Power Systems

Utility service, medium- and low-voltage distribution, standby generation, UPS systems, transfer and switching equipment, and distribution to the rack — including load acceptance and response to loss of source.

Mechanical and Cooling Systems

Chilled water plant, air handling, containment and heat rejection, verified for capacity, balanced distribution, control stability and recovery under design and off-design conditions.

Liquid Cooling and High-Density Infrastructure

Coolant distribution, direct-to-chip and rear-door cooling, loop integrity, and leak detection and containment.

Controls, Protection and Monitoring

Building and electrical power management systems, protection and control settings, and alarm and sequence verification.

Integrated Facility Response

The behaviour of all systems together under simulated failure, including transfer, ride-through and recovery.

The L0–L5 Commissioning Process: Design Review to Integrated Systems Testing

MCE applies a gated six-level framework. Each level defines what is being verified, progressing from design documentation through to the completed facility. A system advances only once the preceding level has been signed off, and progress is tracked and reported to the owner throughout the program.

Design review is where the leverage is. A finding raised against the documentation costs a fraction of the same finding raised during integrated systems testing, and it is the level MCE invests in most heavily.

L0

Design Review

+
Verification of design intent against the Owner's Project Requirements, including redundancy and topology, commissionability, and submittal review.
L1

Factory Testing (FAT)

+
Verification at the manufacturer, covering both the equipment model and the individual units supplied, prior to shipment.
L2

Delivery & Installation

+
Verification of delivered condition and installation quality.
L3

Pre-Functional & Startup (PFT)

+
Verification of readiness for energization and first start, together with review and witnessing of testing, adjusting and balancing (TAB) results.
L4

Functional Performance Testing (FPT)

+
Verification of each system's specified performance and operating sequences under controlled load.
L5

Integrated Systems Test (IST)

+
Verification of the facility as a whole under full dynamic load and simulated failure, through to turnover.

Testing is executed in accordance with NETA ATS, NFPA 110, IEC/IEEE, ASHRAE and AHRI practice.

AI Data Centre and Liquid Cooling Commissioning

High-density GPU deployments introduce cooling infrastructure that traditional air-cooled commissioning does not address. MCE commissions liquid-cooled facilities within the same gated framework, extending it to cover:

Coolant Distribution and Loop Integrity

Verification of distribution units, primary and secondary loops, and loop integrity and cleanliness before liquid reaches live equipment.

Leak Detection and Containment

Functional verification of detection, alarm and isolation response, and of containment provisions, ahead of energization.

Integrated Thermal Control

Verification of the control sequences linking facility cooling, coolant distribution and rack-level cooling as a single coordinated response.

Thermal Performance at Load

Recorded verification of cooling performance and facility efficiency across progressive load steps, to design capacity and beyond.

Commissioning Deliverables: Reports, Test Records and Turnover

Commissioning produces the record that supports acceptance, operation and future accountability. MCE's deliverables include:

Design Review Pack

An in-depth review of the design across every critical system — power, cooling, controls, fire and life safety — issued as a consolidated design pack for a resilient build: redundancy and topology, single points of failure, commissionability, and what must change before construction commits it. Written to the robustness of each critical system and reviewed against the owner's availability objectives.

Commissioning Plan

Scope, responsibilities, level definitions, test sequence and acceptance criteria, issued before work begins.

Test Documentation

Executed checklists and test scripts, witnessed and dated, recording measured results against acceptance criteria.

Deficiency Register

Maintained throughout the program, prioritized, and tracked to closure prior to substantial completion.

Final Commissioning Report

The consolidated verification record, including performance results, failure-mode results and compliance data.

Turnover Package

As-built records, O&M documentation, warranty registers and operating procedures, compiled through the program rather than at its close.

Operational Readiness support — training, procedures and staffing review — is available as an optional addition to the program.

The commissioning record remains the owner's evidence of verified performance long after project completion. The record can support insurance, financing, operations, and regulatory discussions.

Scope note: MCE acts as Commissioning Authority on the owner's behalf. MCE directs and witnesses commissioning activities and verifies the results. MCE does not perform installation, energisation or equipment operation, does not direct the contractor's means and methods, holds no design or construction interest in any project it commissions, and does not act as engineer of record.

Commissioning a new build or an existing facility?

Independent verification, on the owner's side, from design review through integrated systems testing.