Request Consultation
Insights

Data Centre Engineering Insights

Insights from Mission Critical Engineers on data centre commissioning, power systems and mission-critical electrical engineering.

Independent research on power, cooling, interconnection and failures in AI-scale data centres. Mission Critical Research
Latest · Data Centre

Who Owns the Liquid Cooling Loop?

A direct-to-chip cooling loop is built in stages by four or five companies, from design to the day the racks are connected. Who does what, where one company hands over to the next, and where responsibility tends to fall through.

November 10, 2026
Data Centre

When Liquid Cooling Fails: The Seconds That Matter

When a coolant pump or CDU stops, the GPUs in a direct-to-chip liquid-cooled AI data centre have seconds. How the loop works, why it loses cooling in ways an air-cooled room never did, and what ride-through has to prove.

October 27, 2026
Commissioning

What does a commissioning project need?

Before anything is tested, a commissioning project needs a team that knows how these facilities fail, the owner's requirements, a commissioning plan, design reviews and a test for every piece of equipment. The team is ours. The rest is MCX™.

October 22, 2026
Data Centre

Liquid Cooling, Explained: Five Technologies and Where Each Fits

Five liquid cooling technologies for AI data centres: rear doors, single- and two-phase cold plates, single- and two-phase immersion. What each is, where it fits, and what commissioning must prove before the first rack depends on it.

October 8, 2026
Commissioning Field Note

Load Bank Testing in Data Centre Commissioning: Six Problems We See on Almost Every Project

Six load bank testing problems that derail data centre commissioning — generator tests that prove nothing, cooling validation that misses hot spots, and an IST deadline nobody is protecting. If two feel familiar, let's talk.

July 20, 2026
Commissioning Field Note

The Commissioning Illusion: What Your Vendor Start-Up Report Doesn’t Tell You

Vendor start-up proves each piece of equipment in isolation. An independent commissioning authority proves the facility works as one integrated system, and checks what self-witnessed IST scripts miss.

June 25, 2026
Data Centre Field Note

Is Your Data Centre AI-Ready? Probably Closer Than You Think

AI-ready is not a certification. It is a set of thresholds across five systems (power density, structural load, cooling, network and fiber density, and monitoring), and an assessment shows which of them have headroom before any capital is committed.

May 21, 2026
Electric Fundamentals Guide

Load Tap Changers: How Transformers Regulate Voltage Under Load

How on-load tap changers regulate transformer voltage under load: the turns ratio, the two-stage switching sequence, resistor, reactor and vacuum transition elements, and what the mechanism means for maintenance and condition monitoring.

May 12, 2026
Data Centre Guide

Data Centre Transformer Protection: The Critical Role of the 87T Differential Relay

As AI data centres deploy hundreds of medium-voltage transformers, electrical protection has shifted from a substation specialty to mission-critical infrastructure design. Explore the complete transformer protection stack and the engineering mechanics of the 87T differential relay.

April 9, 2026
Data Centre Guide

The Engineering Guide to Mission-Critical UPS Systems: Static, Hybrid, and DRUPS Explained

How a UPS bridges the gap to backup power, how a double-conversion UPS behaves in online, battery and bypass mode, and how static, flywheel, hybrid and DRUPS architectures compare.

November 20, 2025
Commissioning Field Note

The Commissioning Checkbox: Why Feeder and Cable Testing Is Your Facility’s Biggest Blind Spot

Feeders and cables are the most vulnerable assets in a mission-critical facility. Four tests go beyond code-minimum commissioning: advanced insulation diagnostics, conductor and connection integrity, ground fault protection validation, and load performance under real operating conditions.

September 26, 2025
Electric Fundamentals

Mastering Phase Rotation: OESC Compliance, Safety, and Operational Integrity

A technical white paper on phase rotation in three-phase systems in Ontario: the principles, a risk hierarchy of equipment, the OESC provisions that apply, a five-part field verification process, and the economic and legal stakes.

September 2, 2025
Data Centre Field Note

Is Your Data Centre Ready for the Demands of High-Density GPUs?

Racks drawing 50kW, 70kW or more introduce failure points that standard assessments can't account for. Three questions on cooling, power distribution and heat rejection to answer before you scale a high-density GPU deployment.

August 24, 2025
Next step

Have a data centre project in planning?

Tell us about your project, and we will come back to you.